完整版 轻型井点降水方案

阅读: 评论:0

XX工程公司
年月日
一、工程概况···································································2
二、编制依据····································································2
三、降水方案选择·······························································2
四、井点降水相关计算先解风情后解衣·························································3
五、主要降水设备·······························································6
六、施工工期·····································································7
七、井点施工方法·······························································7
八、质量标准及质量保证措施················································8
九、危险点分析································································10
十、安全生产及文明施工措施···············································10
十一、环保措施································································11
一、
工程概况sap2000
本期设计为2×600MW亚临界汽轮发电机组。
工程地质情况:本工程持力层采用圆砾层做持力层圆砾层顶一般埋深3.0m~4.5m,
一般厚度6.5m~9.5m细中砂层层顶埋深一般为10.0m~13.0m。一般厚度5.0m~7.0m。圆砾分布于层之下。层顶一般埋深15.0m~18.0m。粘土(残积土)稍湿坚硬覆于凝灰岩之上最大厚度大于6.8m。
二、编制依据
《火电施工质量检验及评定标准》
《电力建设施工及验收技术规范》
《建筑施工计算手册》
临时土方开挖图纸
三、角蜡蚧上海南市区降水方案选择
该项目地处伊敏河畔,属砂砾地质结构,渗透系数为150m/天,容水量大,受降水影响地下水位波动变幅1-2m。枯水期在-6m左右。而本工程大部分建筑物埋深在-6m,处于临界状态,丰水期就无法施工,本工程采取的措施是:采用明沟、集水井的方式进行作业层表
面水的降水。在枯水期柱、基础底脚施工完、回填完,防止丰水期淹没,以减少降水施工的降水费用。基础埋深超过-6m的,采用局部井点降水。
蒋廷探本工程主厂房基础底标高为-5.0m,不须采用井点降水,而循环水泵坑及汽轮机基础底标高为-7.5m,可采用轻型井点降水。基础平面基底长度约为50m,宽度约为36m。基础埋深为见施工图,地面持力层为圆砾层,井点降水可以避免大量涌水、冒泥、翻浆,而且在砂砾地层中开挖基坑时,可防止流砂现象发生,渗流向下改善土的性质,使基底土质更加密实,结合本工程基础施工主要在枯水期期间,周期较长的特点,采用轻型井点降水法,沿建筑物环状布置进行人工降水。同时基坑二角设集水箱配合4台QY-3.5型潜水泵排除明水的方法。
四、井点降水相关计算
1、井点管的埋设深度
H≥H1+h+iL+l
式中H——井点管的埋设深度(m)
H1——井点埋设面至基坑底面距离(m)取3.0m
h——基坑中央最深挖掘面至降水曲线点的安全距离(m)取1.0m
L——井点管中心至基坑中心的短边距离(m)取27
i——降水曲线坡度取1/10
l——滤管长度(m)取1.2
H≥3.0+1.0+27×1/10+1.2=7.9m取8m
2、涌水量计算
Q=1.366K
Q——井点系统总涌水量(m商科3/d)
K——渗透系数(m/d)取150
H——含水层厚度(m)计算暂取11m
R——抽水影响半径(m)计算取91
S——水位降低值(m)取1.2,地下水位取6.8m
XO——基坑设想半径(m)计算取24
本工程以无压非完整井计算
Q=1.366×150
=8818m3/d
3、计算井点管数量和间距
单井出水量q=65πdl×3K
=65×3.14×0.05×1.2×3150
=65m3/d
需井点管数量:
n=1.1Q/q=149根
基坑四角处及机械入口处井点管应加密,则采用的井点管数量为149+32=181根
井点管间距平均为D=2×86/(181-1)=0.96m,取1.0m,机械入口处井点管即泵1泵6的井点管间距为0.8m。
布置时,为使机械挖土有开行路线,宜布置成端部开口(即留6根井点管距离),因此实际需要井点管数量为:
n=2×66/1+40/0.8-5=177根
4、校核水位降低数值:
h=102-8818/(1.366×150)×(Lg91-Lg24)
=8.7m
实际降低水位S=10-8.7=1.3m
此值与需要降低水位数值1.2m相符,故布置可行。
5、结论
根据标书的水位情况目前水位在主厂房零米以下6.0米左右以及现场测量实际情况为-6.85m,本工程井点管深度在-8.0m(从-5.0m处向下埋管)间完全能保障降水要求。降水井点布置见汽机房基础降水井点平面布置图、轻型井点管埋深剖面图。
五、主要降水设备
1、本工程共设轻型射流泵(JSJ60)6台,工作水流45m3/h,离心泵(3BL-9)6套,电动机(JO2-42-2)6台,冲孔管4套,QY-3.5型潜水泵4台
2、射流泵轻型井点降水井点为167根,总管(其中导流总管120m)长度为320m,配用循环
水箱(1200×1200×1500×4mm)2个

本文发布于:2023-06-27 05:26:06,感谢您对本站的认可!

本文链接:https://patent.en369.cn/xueshu/135406.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:降水   井点   施工   基础   基坑   工程
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2022 Comsenz Inc.Powered by © 369专利查询检索平台 豫ICP备2021025688号-20 网站地图